Every contract in the company profile, 34 in total, running from 2007 to 2023. Figures and clients are reproduced as recorded in "Section 9.5 — Jobs Handled by Arthur Ferdinand Limited".
Replacement of Bad 24” Valve at Oben Node Aghara AGI PS 1 Escravos – Lagos Gas Pipeline
Completed
Project detail
Emergency Construction of 20″ by 8km Crude Oil Pipeline from Jetty to WRPC Tank Farm
Ongoing (90% complete)
Project detail
Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (ikpeba.8km 36″ River Crossing / Swamp)
Completed
Project detail
Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (30″ /36″ ) Hot Tapping
Completed
Project detail
Expansion of Escravos Lagos Gas Pipeline Project- Phase 1 (24″ NGC – WGTP Station Approach)
Completed
Project detail
Expansion of Escravos Lagos Gas Pipeline Project- Phase 2 (oregha 30″ River Crossing / Swamp)
Completed
Project detail
Escravos Gas Project Phase 3 – (fabrication / Blasting and Painting of Module 65)
Completed
Project detail
Complete contract list
| Project | Client | Discipline | Date | Status |
|---|---|---|---|---|
| Project Management Office Security/Surveillance of Pipeline in Western, Central and Eastern Corridor | Inter-Atlas Synergy Ltd, NNPCL | Surveillance & Security | AUGUST 9, 2023 | Ongoing |
| Replacement of Bad 24” Valve at Oben Node Aghara AGI PS 1 Escravos – Lagos Gas Pipeline | Nigeria Gas Company (NGC) / Zakhem | Pipeline & Valves | JANUARY 2020 | Completed |
| Expansion of Warri Gas Treatment Plant | Nigeria Gas Company (NGC) / Zakhem | Other Works | November 2019 | Ongoing |
| Leak Repair of 36″ Escravos – Lagos Gas Pipeline | Nigeria Gas Company (NGC) / Zakhem | Pipeline & Valves | November 2019 | Completed |
| Supply of Processing Equipment Spare Parts for Oredo Early Production Facility (epf2) at Oredo Flowstation in OML 111 | Nigerian Petroleum Development Company Limited (NPDC) | Gas Plants & Facilities | MAY 2019 | Completed |
| Surveillance, Security, Maintenance and Repairs of Trans Forcados Pipeline | NPDC / OMS | Surveillance & Security | APRIL 2019 | Ongoing |
| Surveillance, Security, Maintenance and Repairs of OML 40 Pipeline | NPDC / OMS | Surveillance & Security | 2018 | Ongoing |
| Repair of Crude Oil Storage Tank 63 | Warri Refining & Petrochemical Limited | Refinery & Tankage | MAY 2017 | Completed |
| Repair of Crude Oil Storage Tank 81 | Warri Refining & Petrochemical Limited | Refinery & Tankage | MAY 2017 | Completed |
| Surveillance, Security, Maintenance and Repairs of NCTL | Aiteo E&P | Surveillance & Security | NOVEMBER 2017 | Completed |
| Emergency Construction of 20″ by 8km Crude Oil Pipeline from Jetty to WRPC Tank Farm | WRPC | Pipeline & Valves | FEBRUARY 2016 | Ongoing (90% complete) |
| Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (fabrication / Installation of AGI/ 36″ LBV) | NNPC | Pipeline & Valves | JANUAR Y 2015 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (fabrication / Installation of Two 36″ LBV ) | NNPC/ Zakhem | Pipeline & Valves | JANUAR Y 2015 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (ikpeba.8km 36″ River Crossing / Swamp) | NNPC | Pipeline & Valves | JANUAR Y 2015 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (ologbo /Oghara 4.8km 36″ River Crossing / Swamp) | NNPC / Zakhem | Pipeline & Valves | JANUARY 2015 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project- Phase 2 (hydro Texting of 36″, 51km from Pko to Kp51) | NGC | Pipeline & Valves | NOVEMBER 2015 | Completed |
| Repair of Crude Oil Storage Tank 60 | Warri Refining & Petrochemical Limited | Refinery & Tankage | OCTOBER 2014 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (36″ 70 KM) | NNPC / Zakhem | Pipeline & Valves | NOVEMBER 2014 | Completed |
| Edo Gas Development Project | Nigeria Gas Company (NGC) | Other Works | JUNE 2014 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project – Phase 2 (30″ /36″ ) Hot Tapping | NNPC / Zakhem | Pipeline & Valves | MARCH 2013 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project – Phase 1 (30″ NGC – WGTP Station Approach) | N.G.C. / Zakhem | Pipeline & Valves | SEPTEMBER 2011 | Active |
| Expansion of Escravos Lagos Gas Pipeline Project- Phase 1 (24″ NGC – WGTP Station Approach) | N.G.C. / Zakhem | Pipeline & Valves | SEPTEMBER 2011 | Completed |
| Expansion of Escravos Lagos Gas Pipeline Project- Phase 2 (oregha 30″ River Crossing / Swamp) | NNPC / Zakhem | Pipeline & Valves | JANUARY 2011 | Completed |
| Escravos Gas Project Phase 3 – (fabrication / Blasting and Painting of Module 65) | Chevron / HHI | Fabrication & Coatings | APRIL 2010 | Completed |
| Modification of 3” PC C3 Return Line to Tank Farm | Warri Refining and Petrochemical | Refinery & Tankage | FEBRUARY 2009 | Active |
| Emergency Linking of PC Wells (wells Abc) to D951/Fire Water Tank | Warri Refining and Petrochemical | Refinery & Tankage | JANUARY 2008 | Active |
| Nitrogen Purging Chevron Gas Plant | HHI EGP3 Project | Pipeline & Valves | JAN 2008 | Active |
| Piping of Waste Water Plant | Warri Refining and Petrochemical | Refinery & Tankage | FEB 2008 | Active |
| Repair of 24″ Pipe Near Gas Tank Farm | Warri Refining and Petrochemical | Refinery & Tankage | JANUARY 2008 | Active |
| Repair of 24” Kero Pipe at Jetty | Warri Refining and Petrochemical | Refinery & Tankage | MAY 2008 | Active |
| Repair of FCC Debutanizer Column (16- )-06) in Fuel Plant | Warri Refinery and Petrochemical | Refinery & Tankage | OCTOBER 2008 | Active |
| Repair of Loading Arms (hot Tapping) | Warri Refining and Petrochemical | Pipeline & Valves | JANUARY 2008 | Active |
| Construction of a Jump-Over Line from Fuel Oil to the Condensate Line for the Transfer of Light Slop Oil from 301-Tk-35/36 to the Crude Tanks | Warri Refining and Petrochemical | Refinery & Tankage | DECEMBER 2007 | Active |
| Instrumentation Work at Alakiri Gas Plant | SPDC / Lee Engineering | Gas Plants & Facilities | Active |
Some pages of the source document listed more than one contract; where two entries carried an identical title and client they have been merged. Typos in the source document (for example "TREAMENT", "RIPAIR", "COLUM") have been corrected in the titles above.